Maharashtra
2011
246
 MW
1.2
 MT/y

MIHAN Power Project

Profitable?
No
 
Profitable?
Yes
 
Annual CO2 emissions saved
1.2
MT / year
Total W-S-B investment need
0.515
Bn. $

Investment breakdown

This power plant can be profitably converted to S-W-B with a $0.515 Bn total investment.
This power plant can be converted to S-W-B with a $0.515 Bn total investment.

Solar
379
M. $
Wind
111
M. $
Battery
24,120
M. $

Production costs

5.2
ct/kWh
Production cost of coal (Source: IEA World Energy Outlook 2022; adjusted)
3.45
ct/kWh
Production cost of renewable energy

Technical breakdown

Renewables installed capacity

Solar
583
MW
Wind
120
MW
Battery
21
MWh

Renewable energy production

Share of Solar-Wind to match current coal production
77.7
%
22.3
%
Solar
Wind

Renewables area

Total area required for Wind-Solar mix*: 5.52 km²
*On sites with a high wind fraction, wind need = total need. Solar panels are placed within the area occupied by wind infrastructure.
4.67
km²
4.27
km²
Area use solar
Area use wind

Environmental conditions

Key environmental conditions around coal plant site (10,000 km2)

These are input values for the SwitchCoal model taken from the following reliable sources:
Solar efficiency rate
1582
kwh/kwp
Mean wind speed
6
m/s

Impact

90%
of the world’s coal power plants can be profitably replaced by  wind-solar-battery plants. 