Dolnośląskie
1971
1948
 MW
11.2
 MT/y

Turów power station

Profitable?
No
 
Profitable?
Yes
 
Annual CO2 emissions saved
11.2
MT / year
Total W-S-B investment need
5.159
Bn. $

Investment breakdown

This power plant can be profitably converted to S-W-B with a $5.159 Bn total investment.
This power plant can be converted to S-W-B with a $5.159 Bn total investment.

Solar
1,201
M. $
Wind
3,739
M. $
Battery
218,795
M. $

Production costs

13.5
ct/kWh
Production cost of coal (Source: IEA World Energy Outlook 2022; adjusted)
4.28
ct/kWh
Production cost of renewable energy

Technical breakdown

Renewables installed capacity

Solar
1848
MW
Wind
2352
MW
Battery
192
MWh

Renewable energy production

Share of Solar-Wind to match current coal production
18.6
%
81.4
%
Solar
Wind

Renewables area

Total area required for Wind-Solar mix*: 83.99 km²
*On sites with a high wind fraction, wind need = total need. Solar panels are placed within the area occupied by wind infrastructure.
14.78
km²
83.99
km²
Area use solar
Area use wind

Environmental conditions

Key environmental conditions around coal plant site (10,000 km2)

These are input values for the SwitchCoal model taken from the following reliable sources:
Solar efficiency rate
1085
kwh/kwp
Mean wind speed
9
m/s

Impact

90%
of the world’s coal power plants can be profitably replaced by  wind-solar-battery plants. 